A DAP quote for refractory bricks needs more than a city and a tonnage. It should name the receiving point, show the packed load on which transport was priced, and explain who handles import clearance and unloading. Two quotes are not comparable if one ends at a terminal and the other ends at your plant gate.
1. Name the handover point before pricing the route
Write DAP [agreed named place and precise handover point], Incoterms® 2020. Give the freight team the site address and the specific gate, warehouse or receiving bay. Add vehicle access, booking rules and receiving hours if they affect delivery. If all you know is the city, label the figure a budget estimate and state which handover point it assumes.
Under DAP the seller arranges carriage to the agreed destination and delivers there with the goods on the arriving vehicle, ready for unloading. The buyer generally handles import clearance, duties and taxes, and arranges unloading; check whether the carriage contract has already included an unloading charge. If you need an unloaded handover or seller-handled import clearance, discuss the appropriate term with your logistics and customs teams. Do not silently price or label that scope as ordinary DAP.
2. Give the carrier the packed load, not just the product weight
| Confirm | Give the freight team | If the information is missing |
|---|---|---|
| Shipment scope | Brick lines, quantities and whether they ship together or in separate lots | Mark the split as provisional and avoid comparing it with a single-shipment quote. |
| Packed load | Pallet or crate count, outside dimensions, gross weight by handling unit, and stacking restrictions confirmed by the packing party | Record assumed pack data. Requote if size, gross weight or shipment count changes. |
| Destination access | Exact receiving point, vehicle restrictions, appointment and receiving window | Use a stated planning assumption, not a guaranteed gate delivery. |
| Clearance and unloading | Import clearance contact, receiving team and who arranges and pays for the unload | Reconcile the contract and carriage quote; do not assume the driver unloads. |
| Rate basis | Included carriage, exclusions, validity and applicable conditions for waiting or storage | Do not compare with a rate that silently covers a different route, scope or period. |
The brick line can show net product weight while the carrier quotes on gross packed weight and dimensions. Ask for a packing list basis and tie it back to the same drawing revision and order quantities rather than carrying over the figures from a similar order.
3. Release the freight quote and the material review separately
Put each of the three decisions on a separate line: material and drawing confirmed, technical documents confirmed, and freight scope confirmed. Record who owns each open point. A complete freight quote does not establish whether a brick suits a furnace zone. A datasheet does not prove which tests will accompany the shipment. Do not describe the combined offer as firm while a material change, required report or delivery assumption could still alter it.
For example, two suppliers quote to the same city. One prices delivery to a freight yard; the other prices a booked arrival at the plant gate. Ask each supplier to reprice the same handover point with the same gross packed load and to show any receiving charges excluded. The example is hypothetical and does not imply a route, rate or guaranteed service.
Frequently asked questions
Does DAP mean import duties and taxes are included?
No. Import clearance and associated duties and taxes are generally the buyer’s responsibility under DAP. Confirm the local procedure and importer with your customs team.
What can I send if I do not yet know pallet dimensions?
Send the confirmed brick list and delivery point, identify the pack data as pending and ask whether any quoted freight is budgetary. Ask for confirmation after the packing plan is available.
Does a DAP price include an agreed delivery date?
Not by itself. Confirm separately the rate validity, production lead time and the assumed transit and receiving window; distinguish estimates from contractual dates.
Preparing a quotation request
Send the current brick list, drawing revisions, expected shipment split, receiving location and required technical documents. Use the refractory brick RFQ checklist to align the material lines before comparing delivery offers. For review, use the existing request-a-quote page. Availability, documentation, routes and prices remain subject to actual quotation and review.
Sources: ICC Academy, DAP or DDP and DPU or DAP. The checklist is a procurement aid; use the agreed contract and obtain local customs advice where needed.